NE-TECH Begins Hot Commissioning of Two-Line Tyre Pyrolysis Plant in Hungary
🇭🇺 NE-TECH INDUSTRIES has begun hot commissioning at its end-of-life tyre (ELT) pyrolysis facility in Karcag, Hungary
🇭🇺 NE-TECH INDUSTRIES has begun hot commissioning at its end-of-life tyre (ELT) pyrolysis facility in Karcag, Hungary, following completion of construction and cold commissioning across the entire plant. Initial tests have already produced tyre pyrolysis oil (TPO), with regular production targeted for early December 2026.
The facility comprises two pyrolysis reactor lines and a dedicated recovered carbon black (rCB) processing section. Developed in partnership with MOL Group, the project uses NE-TECH's proprietary Continuously Revolving Charge Cycle (CrCC™) technology, based on modular, pre-engineered units.
Commissioning is now progressing across the main process units. The first reactor line is undergoing staged ramp-up on a five-day-per-week test schedule, while hot commissioning of the second line is scheduled for mid-November.
Meanwhile, NE-TECH and equipment supplier Hosokawa Micron B.V. are preparing the final commissioning phase of the rCB finishing line, which includes grinding, pelletising and drying equipment to process recovered carbon black into a finished material.
In parallel, construction of the flue gas purification systems and online emissions monitoring has been completed. NE-TECH is also training the operating team and preparing the infrastructure required for continuous plant operation.
The Karcag facility is part of a wider industrial partnership network involving MOL, Gunvor and Carbon Black Kft. Both reactor lines are targeted to enter regular operation in early December 2026.